The release schedule for AIPS++in the current operational phase is
two releases per year, nominally scheduled for the months of April and
October. This schedule establishes a natural development cycle lasting
approximately six months. The planning activities during each
development cycle proceed by the following stages, starting two weeks
before the date the master distribution for the preceding release is
finalized:
- 1.
- Each person formally responsible for a module or area of
development in the system is asked to prepare a preliminary planning
document describing the module priorities, current status and proposed
development items for the coming development cycle, but without making
any target assignments. A list of deferred or postponed development
items from previous cycles is maintained within the project
documentation system for reference, but the planning is zero-based,
i.e. planning for each cycle is considered afresh with new items
competing for scheduling with deferred or carry-over development items
on the basis of their merit alone at the time of each planning cycle. This
prevents planning inertia, and allows the project to be responsive to
evolving user needs and external advice; however, it does retain
continuity.
- 2.
- The collected planning proposals are circulated internally for
general comment, and to allow other development items to be motivated
from within the consortium.
- 3.
- After this period of comment, the development plan is finalized
in discussions between the project management and the site managers,
with final arbitration by the project management, whose job it is in
this context to ensure that overall project goals and user
requirements are met and external advice is heeded. Target
descriptions and assignments will then be established from the agreed
development items.
- 4.
- The plan becomes final when each site manager, after
consultation with the site Director as required, accepts the agreed
targets for their site. Each target constitutes a work package, and
includes a full description of the task, a time estimate, any other
targets on which it depends, an assigned developer and completion
criteria.
- 5.
- All deferred or postponed items are added to the documented list
of items carried forward to the next development cycle, to be
reconsidered at the start of the next planning cycle. A basic priority
(short-, medium- or long-term) will be assigned to all deferred items,
but are not binding due to the zero-based planning.
- 6.
- The targets for the current cycle are entered in the target
tracking system, which records weekly progress reports from all
developers with assigned targets. These weekly e-mail reports are an
important communication mechanism within the project.
- 7.
- Progress on the plan is monitored and reported by the project
management. Mid-course planning revisions are discouraged, unless a
major planning deficiency is uncovered in implementation. This is to
ensure that the project maintains a focus on delivering the agreed
targets at the end of the development cycle. Items can be submitted at
any time for consideration in the next planning cycle, and are added
to the recorded list of possible future development items.
Next: Releases
Up: Software engineering practices in AIPS++
Previous: Introduction
  Contents
Please send questions or comments about AIPS++ to aips2-request@nrao.edu.
Copyright © 1995-2000 Associated Universities Inc.,
Washington, D.C.
Return to AIPS++ Home Page
2006-03-28