General timeline

There are several steps involved going from active development to generating a release ready ISO image. In general it takes a about of 5 weeks, although if things go well it may be possible to squeeze the whole process into three weeks.
-5 weeks
Slushy Freeze
-3 weeks
Hard Freeze
-2 weeks 2 days
Uprev
-2 weeks
Generate Release Candidate
0
Release to Duplicators