There are several steps involved going from active development to generating a release ready ISO
image. In general it takes a about of 5 weeks, although if things go well it may be possible to
squeeze the whole process into three weeks.
- -5 weeks
- Slushy Freeze
- -3 weeks
- Hard Freeze
- -2 weeks 2 days
- Uprev
- -2 weeks
- Generate Release Candidate
- Make release build
- Test release build
- Patch
- Make ISO image
- Test ISO image
- 0
- Release to Duplicators