- Consolidation and evaluation
- Views on user interfaces are
inherently subjective; a wider pool of scientific users needs to use
and comment on the current automated GUI system, as implemented in
toolmanager, before undertaking a second revision of the user
interface. This feedback needs to be actively sought, and reviewed
during this cycle. This factor, combined with the limited available
resources for toolmanager development, argues for consolidation only
during this development cycle.
- New technology evaluation
- It is appropriate at this point to
evaluate new technology for the Tasking and UI systems.
- toolmanager
- Maintenance of toolmanager, and addition of new
capabilities in the area of integration and scientific
usability. Consolidation of related code in identified areas, and
speed improvements (RM, H, 6 wk).
- Requirements document for revised Tasking/UI system
- Draft
requirements for an upgrade of the current Tasking and User Interface
system. (AK, H, 1 wk)
- Implementation proposal/prototypes for revised Tasking/UI
- Draw up an
implementation proposal and schedule for moving to a revised
Tasking/UI system, including proposed middleware, such as CORBA, and
the associated Glish interface. Includes simple prototyping and
related evaluation. (DS, H, 5 wk).
Next: Basic library
Up: AIPS++ DEVELOPMENT PLAN: Release 1.5
Previous: Glish
  Contents
Please send questions or comments about AIPS++ to aips2-request@nrao.edu.
Copyright © 1995-2000 Associated Universities Inc.,
Washington, D.C.
Return to AIPS++ Home Page
2006-08-01